There are a number of construction activities related to the Center of Excellence project underway at the Innovative Technologies complex that will take place May 14 through May 30.
-At approximately 7 a.m. on Monday, May 21, a crane will be located on the south lawn of E&S west of the main entrance.
From Tuesday, May 22 through Friday, May 25, the first row of parking spaces in lot J will be barricaded. Disability parking will be available at the Biotechnology Building entrance. Trucks will be delivering steel to the main entrance area of E&S and caution is urged around truck traffic. From
-7 a.m. to 4 p.m. during this period, steel will be delivered and set up on the roof. The main entrance and rotunda entrance will be closed during this activity and building occupants and visitors will be directed to use the Biotechnology entrance or the Engineering and Science loading dock entrance during this time. Signs will be used to indicate closures/detours. In case of emergency, all the usual entrances and exits will be available and construction activity will be halted. Throughout the steel delivery/placement, the contractor will set up temporary barriers to keep people clear of the E&S main stair, lobby, and main corridor under the skylights while steel is lifted. This will not take long and we ask for your patience to keep these areas clear and safe.
Contact Lisa Sklener at lsklener@binghamton.edu or 759-8276 or Mike Frisina at mfrisina@binghamton.edu or 585-506-5230 with any questions.
Improvements will be made to Library corridors where the English department offices are located as well as floors above and below. Work will begin after Commencement. The first three weeks will consist of asbestos abatement and ceiling demolition, one week per floor. This means that all offices off of the hallway being abated will not be accessible during that one week period.
This renovation will provide new floor tiles, ceilings, improved lighting, fresh paint and new or refurbished doors to the hallways. There will be inconveniences such as paint smells, construction noise, intermittent limited access during the project. Floors will be re-tiled after 3:30 in the afternoon so that some access can be maintained during the day. The project will be complete before the start of the fall semester.
Contact Mary Ann Fletcher with any questions at mfletch@binghamton.edu or 777-5064.
Sidewalks and building area entrances will be replaced in a number of locations around campus beginning Monday, May 21. The areas are shown as PR3170 on our construction map.
The contractor has given us the following schedule. Note that work may be delayed due to to poor weather.
Contact project coordinator Gary Bendert with any questions at gbendert@binghamton.edu or 777-3196.
The north portion of the Lecture Hall Concourse will close for renovation following Commencement. The project will renovate the north portion of the Lecture Hall along with Lecture Hall 7. This includes the area from Lecture Hall 6 to Lecture Hall 10 and he men's and women's restrooms below. Like the renovation of the south portion which took place last summer, work involves new flooring, ceilings lighting, doors and furniture. The work will be complete in time for the fall, 2012 semester. Contact Jennifer Bourassa with any questions at jbourassa@binghamton.edu or 777-5047.
The access road to Lot M2 from West Drive will be closed beginning Monday, May 21 for emergency repairs. Access to this parking lot and other areas will be noted with detour and direction signs. Repairs are expected to be completed within two weeks. Anyone with questions should contact Don Whittemore at dwhittem@binghamton.eduor 7-5464HTHW Shutdown Extended to May 30 for Some Buildings
The high temperature hot water shutdown will be extended until Wednesday, May 30 for the following buildings only:
The extension is needed due to work on isolation valves for a HTHW project that will take place between Science II and Science III in the coming weeks. Contact project coordinator Jason Williams with any questions at jrwillia@binghamton.edu or 777-6491.
The final phase of the Central Campus Quad project is underway with work on the fountain area. Following Commencement, fencing will be re-located and there will be significant changes in pedestrian traffic.
There will be signage to aid pedestrians through these detours. Work on this project will be complete in November. Contact project coordinator Renee Andrews with any questions a randrews@binghamton.edu or 777-3317.
There will be an electrical shutdown from 7 a.m. to 4 p.m. on Saturday, May 26 affecting the following buildings only:
General guidelines about electrical shutdowns can be found here.
Contact Tom Seidel with any questions at tseidel@binghamton.edu or 777-4468.
There will be plumbing work in the Anderson Center reception room area that including welding and hammer drilling 7 a.m. to 3:30 p.m. from Friday, May 25 through Friday, June 1 and Monday, June 4 through Wednesday, June 6. The work is related to the water line replacement project. Contact project coordinator Don Whittemore with any questions at dwhittem@binghamton.edu or 777-5464.
Demolition of the softball field on the east fields will begin Friday, June 1. The softball facility is being re-located to the west fields as part of the athletic fields upgrade project. Contact project coordinator Mo Afify with any questions at mafify@binghamton.eduor 777-2828University Union North Renovation/Food Service Area Renovation
The north portion of the University Union will be closed for renovation beginning Monday, June 4. There will be temporary access to the Susquehanna Room through Friday, July 13. As of Monday, July 16, the Susquehanna Room will also be closed for construction.
Access and location of the Campus Mail Services window in University Union north will change beginning Monday, June 4. Access will be through University Union West. Signs will direct users to the new location. The change is needed due to the start of the University Union north renovation project. Contact project coordinator Mo Afify with any questions at mafify@binghamton.edu or 777-2828.