Skip header content and main navigation Binghamton University, State University of New York - Physical Facilities

Center of Excellence Construction Activities at ITC May 14-May 30

There are a number of construction activities related to the Center of Excellence project underway at the Innovative Technologies complex that will take place May 14 through May 30.

  • May 14 through May 21 (7 a.m. - 3:30 p.m.)- part of parking lot J and the south sidewalk/patio will be closed so that solar panels may be delivered to the roof.
  • May 18 through May 28- there will be construction in the  Biotechnology AVP Suite work room to run utilities for the new cafe. Some minimal noise and dust may be associated with this work.
  • May 21 through May 30- new cooling towers and steel to support the towers will be placed on the Engineering and Science building(E&S).

-At approximately 7 a.m. on Monday, May 21, a crane will be located on the south lawn of E&S west of the main entrance.
From Tuesday, May 22 through Friday, May 25, the first row of parking spaces in lot J will be barricaded. Disability parking will be available at the Biotechnology Building entrance. Trucks will be delivering steel to the main entrance area of E&S and caution is urged around truck traffic. From

-7 a.m. to 4 p.m. during this period, steel will be delivered and set up on the roof. The main entrance and rotunda entrance will be closed during this activity and building occupants and visitors will be directed to use the Biotechnology entrance or the Engineering and Science loading dock entrance during this time. Signs will be used to indicate closures/detours. In case of emergency, all the usual entrances and exits will be available and construction activity will be halted. Throughout the steel delivery/placement, the contractor will set up temporary barriers to keep people clear of the E&S main stair, lobby, and main corridor under the skylights while steel is lifted. This will not take long and we ask for your patience to keep these areas clear and safe.

  • There will be no work on Monday, May 28.
  • On Tuesday, May 29 and Wednesday, May 30, the cooling towers will arrive and be placed on the roof. The detours/temporary closures for this activity will be the same at those for the steel delivery notes above.

Contact Lisa Sklener at lsklener@binghamton.edu or 759-8276 or Mike Frisina at mfrisina@binghamton.edu or 585-506-5230 with any questions.

Library Corridor Refurbishment Begins May 21

Improvements will be made to Library corridors where the English department offices are located as well as floors above and below. Work will begin after Commencement. The first three weeks will consist of asbestos abatement and ceiling demolition, one week per floor. This means that all offices off of the hallway being abated will not be accessible during that one week period.

  • The second floor abatement will take place the first week after Commencement May 21 through May 27.
  • The first floor will be abated the second week May 28 through June 3.
  • The ground floor will be abated June 4 through June 10.

This renovation will provide new floor tiles, ceilings, improved lighting, fresh paint and new or refurbished doors to the hallways. There will be inconveniences such as paint smells, construction noise, intermittent limited access during the project. Floors will be re-tiled after 3:30 in the afternoon so that some access can be maintained during the day. The project will be complete before the start of the fall semester.

Contact Mary Ann Fletcher with any questions at mfletch@binghamton.edu or 777-5064.

Sidewalk Replacement Schedule May 21-August 14

Sidewalks and building area entrances will be replaced in a number of locations around campus beginning Monday, May 21. The areas are shown as PR3170 on our construction map.

The contractor has given us the following schedule. Note that work may be delayed due to to poor weather.

  • May 21-May 25- The east entrance to the old University Union will be closed while a new entrance-way is poured.
  • May 28-June1- a trench drain and sidewalk will be replaced near the Physical Facilities service drive off West Access Road.
  • June 4-June 15- the doors on the west side entrance of the old University Union will be closed while the entrance area is replaced.
  • June 18-June22- the sidewalk in front of the Lecture Hall will be replaced.
  • June 25-June 29- the sidewalk near the Student Wing will be replaced.
  • July 2-July 6- the sidewalk near Academic A will be replaced.
  • July 9-July 13- the sidewalk on West Drive near Academic B facility will be replaced.
  • July 16-August 3- the sidewalks around Physical Facilities building will be replaced.
  • August 6-August 14- the sidewalk near the Science III service drive will be replaced

Contact project coordinator Gary Bendert with any questions at gbendert@binghamton.edu or 777-3196.

Lecture Hall Concourse Renovation Begins May 21

The north portion of the Lecture Hall Concourse will close for renovation following Commencement. The project will renovate the north portion of the Lecture Hall along with Lecture Hall 7. This includes the area from Lecture Hall 6 to Lecture Hall 10 and he men's and women's restrooms below. Like the renovation of the south portion which took place last summer, work involves new flooring, ceilings lighting, doors and furniture. The work will be complete in time for the fall, 2012 semester. Contact Jennifer Bourassa with any questions at jbourassa@binghamton.edu or 777-5047.

Lot M2 Access Road Closure Begins May 21

The access road to Lot M2 from West Drive will be closed beginning Monday, May 21 for emergency repairs. Access to this parking lot and other areas will be noted with detour and direction signs.  Repairs are expected to be completed within two weeks.  Anyone with questions should contact Don Whittemore at dwhittem@binghamton.eduor 7-5464HTHW Shutdown Extended to May 30 for Some Buildings

HTHW Shutdown Extended to May 30 for Some Buildings

The high temperature hot water shutdown will be extended until Wednesday, May 30 for the following buildings only:

  • Events Center- no heat, no hot water
  • Physical Facilities- no heat, no hot water
  • West Gym- no heat, no hot water

The extension is needed due to work on isolation valves for a HTHW project that will take place between Science II and Science III in the coming weeks. Contact project coordinator Jason Williams with any questions at jrwillia@binghamton.edu or 777-6491.

Central Campus Quad

The final phase of the Central Campus Quad project is underway with work on the fountain area. Following Commencement, fencing will be re-located and there will be significant changes in pedestrian traffic.

  • Access from parking lot C to the Quad will be closed
  • Access across the Quad from the Science Library to Fine Arts and the Anderson Center will be closed
  • Pedestrians looking to travel from the University Union or Library to Parking Lot C or the West Gym will be directed through Fine Arts and the Anderson Center or through the Science Library and Science III Building/ Green House ramp.

There will be signage to aid pedestrians through these detours. Work on this project will be complete in November. Contact project coordinator Renee Andrews with any questions a randrews@binghamton.edu or 777-3317.

Electrical Shutdown May 26

There will be an electrical shutdown from 7 a.m. to 4 p.m. on Saturday, May 26 affecting the following buildings only:

  • CIW (Cayuga, Mohawk,Onondaga, Oneida, Seneca, Iroquois/Tuscarora)
  • Dickinson (O'Connor/Johnson, Rafuse/Digman, Whitney/Champlain)
  • East Camus Housing- CONTRUCTION SITE ONLY
  • Harpur Ferry Garage
  • Health Services
  • Susquehanna Community (Brandywine, Choconut, Nanticoke, Glenwood)
  • Old University Union

General guidelines about electrical shutdowns can be found here.

Contact Tom Seidel with any questions at tseidel@binghamton.edu or 777-4468.

Anderson Center Reception Room Plumbing Work May 25 - June 6

There will be plumbing work in the Anderson Center reception room area that including welding and hammer drilling 7 a.m. to 3:30 p.m. from Friday, May 25 through Friday, June 1 and Monday, June 4 through Wednesday, June 6. The work is related to the water line replacement project. Contact project coordinator Don Whittemore with any questions at dwhittem@binghamton.edu or 777-5464.

Softball Field Demo Begins June 1

Demolition of the softball field on the east fields will begin Friday, June 1. The softball facility is being re-located to the west fields as part of the athletic fields upgrade project. Contact project coordinator Mo Afify with any questions at mafify@binghamton.eduor 777-2828University Union North Renovation/Food Service Area Renovation

University Union North Closure/Susquehanna Room Closure/Campus Mail Service Access

The north portion of the University Union  will be closed for renovation beginning Monday, June 4. There will be temporary access to the Susquehanna Room through Friday, July 13. As of Monday, July 16, the Susquehanna Room will also be closed for construction.

Access and location of the Campus Mail Services window in University Union north will change beginning Monday, June 4. Access will be through University Union West. Signs will direct users to the new location. The change is needed due to the start of the University Union north renovation project. Contact project coordinator Mo Afify with any questions at mafify@binghamton.edu or 777-2828.

Twitter icon links to Binghamton University's Twitter page YouTube icon links to Binghamton University's YouTube page Facebook icon links to Binghamton University's Facebook page
Bold, Brilliant, Binghamton - The Campaign for Binghamton University

Last Updated: 5/24/12