Repairs to Dickinson Storm Water Line Update Nov. 30

Work to repair the damaged Dickinson storm line continues to make progress. About 80% of the new storm line is in place and the contractor has back-filled and performed soil compaction and testing in those areas. A large manhole is being installed this week and once that is in place, the remaining sections of storm line will be laid and the site back-filled. The contractor will continue to work extra hours and the remaining work this year will take about two weeks to complete, weather permitting.

Crane Work East Drive Lane Restrictions Nov. 30 and Dec. 1

A crane will be on site at Bingham Hall to lift panels into place for a chimney that has been constructed there as part of the ECH boiler project. East Drive near Bingham will be reduced to one way traffic from 7 a.m. to 5 p.m. on Monday, Nov. 30 and Tuesday, Dec. 1. Flag persons will control traffic during this time. The roadway will be open to two way traffic in the evening. The crane will be parked overnight Monday, Nov. 30 in the University Union loading dock area. State service and a few other parking spaces will be taken off line to accommodate the crane parking. Contact project coordinator Gregg Konnick with any questions at or 777-2598.

Work on Enclosure Affects COE Nov. 25-Dec.1

Contractors will be building and enclosure to protect the Center of Excellence during the structural tie-in to the Smart Energy Research and Development facility from Wednesday, Nov. 25 through Tuesday, Dec. 1. There will be some noise during this work which may affect student office 1405. A desk in the area will be moved prior to the work. Contact project coordinator Lisa Sklener at or 759-8276.

Repairs to Dickinson Storm Water Line Update Nov. 16

Work to replace the damaged storm line in the Dickinson Community continues this week. Work was delayed after heavy rain last week while the contractor waited for soil on site to dry. A temporary pipe was put in ahead of the rain last week which aided in the site drying out more quickly. Work this week will focus on putting in new access paths to the site so work can be expedited, stone and pipe deliveries and installing some new storm line. It will take about two weeks to complete the storm water line installation. A large manhole will be delivered later this month and be installed. While the weather is favorable, the contractor will be worker overtime and will be on site from 7 a.m. to 8 or 9 p.m. Overall work at the site is expected to be complete in early December, weather permitting.

Center of Excellence B-pod Renovations Begin August 31

Renovations of the B-pod area on the first floor of the Center of Excellence will begin Monday, August 31. The work may create dust, noise and vibrations. Temporary protection will be installed to limit impacts to building occupants as much as possible. The project is scheduled for completion December 11. Contact project coordinator Laura Graden with any questions at or 777-3375.

Last Updated: 11/30/15